February 25 Construction Update
March 6, 2025
Welcome to the February construction update in 2025. The services and finishes trades are continuing up the building, with final finishes to Level 8 underway.
Read MoreJanuary 25 Construction Update
February 3, 2025
Welcome to the January construction update in 2025. The development team's defect inspections commenced on Levels 1 and 2. Levels 3 and 4 is anticipated to follow in early February
Read MoreDecember 24 Construction Update
January 6, 2025
Welcome to the December construction update in 2024. Apartments on Levels 1 and 2 have progressed to defect inspection stage.
Read MoreNovember 24 Construction Update
December 9, 2024
Welcome to the November construction update in 2024. Balustrades are complete to Level 8 with scaffold stripping and external facade finishes working together down the building revealing Marin's facade.
Read MoreOctober 24 Construction Update
November 1, 2024
Welcome to the October construction update in 2024. The Landsborough Ave streetscape works commenced.
Read MoreSeptember 24 Construction Update
September 30, 2024
Welcome to the September construction update in 2024. The residents' pool and recreational area structure has been completed on Level 1.
Read MoreAugust 24 Construction Update
September 2, 2024
Welcome to the August construction update in 2024. The roof slab was poured, topping out the Marin structure.
Read MoreJuly 24 Construction Update
August 2, 2024
Welcome to the July construction update in 2024. Levels 7 and 8 slab pours are completed.
Read MoreJune 24 Construction Update
July 2, 2024
Welcome to the June construction update in 2024. Level 7 slab pours have commenced.
Read MoreMay 24 Construction Update
June 3, 2024
Welcome to the May construction update in 2024. Level 5 slab pours are completed.
Read MoreApril 24 Construction Update
May 2, 2024
Welcome to the April construction update in 2024. Level 4 slab pours are now complete.
Read MoreMarch 24 Construction Update
April 2, 2024
Welcome to the March construction update in 2024. Formwork has commenced on level 4.
Read MoreFebruary 24 Construction Update
March 4, 2024
Welcome to the February construction update in 2024. The first level slab is now complete.
Read MoreJanuary 24 Construction Update
January 31, 2024
Welcome to the first construction update in 2024. Formwork has commenced for the first level of apartments at Marin.
Read MoreNovember Construction Update
December 1, 2023
Welcome to the November construction update. Construction of Marin is progressing in line with our target program.
Read MoreOctober Construction Update
October 27, 2023
Welcome to the October construction update. Marking an exciting milestone, the final basement slab pours and the first suspended ground floor slab were completed this month.
Read MoreSeptember Construction Update
September 28, 2023
Welcome to your September construction update. The basement slab pours have commenced and are progressing well on Marin site.
Read MoreAugust Construction Update
August 29, 2023
Welcome to your August construction update. Progress continues well this month with lots of activity on the Marin site including the installation of the tower crane. The piling rig has been removed, and the groundwork is underway in preparation for the basement slab pour.
Read MoreJuly Construction Update
July 15, 2023
Welcome to your July construction update. Progress onsite continues well this month with the installation of the capping beam now 90% complete. Our team is diligently working on the basement excavation, with the ramp installation in progress.
Read MoreJune Construction Update
June 4, 2023
Welcome to your June construction update. Progress onsite at Marin continues well this month with the capping beam construction now 80% complete and the bulk excavation for the basement is progressed. The team are diligently carrying out this essential task to prepare the foundations for the upcoming construction phases.
Read MoreMay Construction Update
May 15, 2023
Welcome to the May construction update as we enter the cooler months at Scarborough. Progress at Marin continues well this month with the piling rig used for retention piles demobilising at the end of the week. Formwork, reinforcement, and pouring of concrete for the capping beams are currently underway. This critical phase of the project is progressing smoothly.
Read MoreApril Construction Update
April 4, 2023
Welcome to your April construction update. There has been a hive of activity this month on the Marin site as bulk earthwork and excavation has now commenced, laying the groundwork for the project. This momentous occasion was marked with our official SOD turning with our Traders In Purple project team.
Read MoreReady, Set, Build
March 9, 2023
Following the outstanding sales success of Main Scarborough, Traders In Purple is delighted to announce the commencement of construction. We are excited to announce that early inground stormwater works will commence onsite later this month in March 2023.
Read More