May 15, 2023
May Construction Update
Welcome to the May construction update as we enter the cooler months at Scarborough. Progress at Marin continues well this month with the piling rig used for retention piles demobilising at the end of the week. Formwork, reinforcement, and pouring of concrete for the capping beams are currently underway. This critical phase of the project is progressing smoothly.
Marking an exciting milestone, we will commence the basement bulk excavation next week, which is estimated to last approximately four weeks.