Welcome to your October construction update. Traders In Purple is pleased to share the following update regarding construction progress at Marin.
In October, the Landsborough Ave streetscape works commenced. We saw the completion of the BBQ and pool structure, with ongoing preparations for the structure’s roof installation, and rendering and waterproofing of the Level 1 garden beds. In the Level 1 apartments, wardrobes and appliances have been fitted, and installation of floor linings commenced. On Level 2, tiling is complete, shower screens, wardrobes and joinery installed in preparation for floor linings and appliance installations to follow.
On Level 3, joinery and tiling has progressed and electrical fit-off completed, while Level 4 entered the carpentry and pre-paint stages. On Level 5, internal linings and plastering is complete. On Level 6, internal services rough-in, party fire walls and glazing install is complete and on Level 7, glazing is complete and internal framing underway. On Level 8, the installation of the feature soffit, glazing and high-level services is complete. The roof is partially waterproofed, with solar panels and 50% of the air conditioning condenser units installed.
Looking ahead to November, the construction team will focus on finishing the waterproofing treatment to the roof and install the building’s electrical, mechanical, and hydraulic services on the roof. The resident lift installation will continue and the fit out of the resident amenities will commence. In the apartments, partitioning, glazing, services and internal finishes will continue up the building.