Welcome to your May 2024 construction update. Traders In Purple is pleased to share the following update regarding construction progress at Marin.

As we enter the cooler months, the construction team continue to make great progress. The slab pours to Level 5 are now complete and the site team are forming in preparation for Level 6 slab pours.

At Level 1, the internal services rough-in, fire walls and glazing install is complete and the framing to internal walls and ceiling has commenced. The services rough-in and framing continues on Level 2. At Level 3, the construction team have commenced final inspections of the structure, ready for the back propping to be removed and services rough-in to commence. Formwork continues on Levels 4 through to 6. The mains power has been energised to site and the temporary generator has been decommissioned and removed from site.

Looking ahead to June, the construction team anticipate Level 6 slab pours will be completed and Level 7 pours will commence. Partitioning, glazing and services installation will continue up the building.

For enquiries or to book an appointment, please contact our sales team on 0477 432 432

Back to all articles