July 2, 2024

June 24 Construction Update

June 24 Construction Update

Welcome to the June 2024 construction update. Traders In Purple is pleased to share the following update regarding construction progress at Marin.

The building is taking shape along the Scarborough waterfront. The construction team has completed Level 6 slab pours and has commenced pours on Level 7. Working up the building, on Level 1 glazing and internal framing is completed and plastering and carpentry is underway. On Level 2, internal services rough-in, fire walls and glazing is complete and internal framing has commenced. On Level 3, the construction team continues services rough-in and wall framing. On Level 4,  final inspections of the structure have commenced, ready for the back propping to be removed and services rough-in to begin. The formwork on Levels 5 through to 7 continues.

Looking ahead in July, the slab pours will continue on Level 7. The team will form Level 8 in preparation for slab pours. We anticipate Level 8 and half of the roof slab will be poured in July. Partitioning, glazing and services rough-in will continue up the building.

For enquiries or to book an appointment, please contact our sales team on 0477 432 432

Back to all articles